The Richmond Street Reconstruction Project is a one year construction project spanning from Dundas to York along Richmond. This project is split into three phases:

King to York

  • Phase 1 construction begins: Spring 2020
  • Phase 1 construction ends: Summer 2020

King at Richmond Intersection

  • Phase 2 construction begins: Summer 2020
  • Phase 2 construction ends: Summer 2020

Dundas to King

  • Phase 3 construction begins: Summer 2020
  • Phase 3 construction ends: Fall 2020

Construction will begin on May 4th, until October 31st 2020. The following detour will apply during all 3 stages:

Detour

Routes 4, 6, 15, 104*

Northbound – North on Richmond, Right on York, Left on Wellington Left on Queens, Right on Richmond to Regular Route

Southbound – South on Richmond, Right on Queens, Left on Ridout, Left on York, Right on Richmond to Regular Route

 

*If Regular service is reintroduced within the construction timeline*