Route 9 & Route 31 Changes – September 1, 2019

Current Routing

Approved Routing

Route 9 changes will serve the intersection of Wonderland and Fanshawe Park Roads and provide two-way service along Limberlost.

Route 9 will no longer be interlined with Route 6 in the evenings and will operate to downtown during all time periods.

Route 31 will be modified to operate along Aldersbrook Road to the Hyde Park Power Centre.  The route will now operate as a stand-alone route, no longer interlined with Route 19 and 32

Service through the Orchard Park neighbourhood will be removed, leaving a small section of the area more than 400m to transit stop.

With changes, there is a loss of transit service on Aldersbrook Road east of Aldersbrook Gate; however, there are only 30 daily riders who currently board or alight in this area and the majority will be within 400 metres of the proposed Route 9 stops.

The elimination of the Route 31/32 interline will remove a direct connection between the Hyde Park Centre/Aldersbrook Road and Kipps Ln/Huron & Highbury. 

Route 32 will be eliminated as of September 1, 2019 with the new Routes 27 and 34 providing service to portions of the former route. 

Frequency – Route 9 

Weekday Time Period Early AM AM Peak Base PM Peak Early Evening Late Evening
Proposed Headway 17 16 15 15 22 32
Existing Headway 15 15 15 15 30 30
Saturday Time Period Early AM Base AM Peak PM Peak Early Evening Late Evening
Proposed Headway 60 32 23 25 32 30
Existing Headway 60 30 30 30 30 30
Sunday Time Period Early AM Base Peak Evening
Proposed Headway 60 33 23 30
Existing Headway 60 30 30 30

Frequency – Route 31 

Weekday Time Period Early AM AM Peak Base PM Peak Early Evening Late Evening
Proposed Headway 48 28 27 30 55 48
Existing Headway 30 30 30 30 60 60
Saturday Time Period Early AM Base Peak Early Evening Late Evening
Proposed Headway 50 25 27 52 48
Existing Headway 35 30 30 60 60
Sunday Time Period Early AM Base Peak Evening
Proposed Headway 50 50 50
Existing Headway 60 60 60