Staff Report #6 – Re: Recosted 2019 Budget Program

Staff Report #6

March 27, 2019

To All Commissioners

Re: Recosted 2019 Budget Program

Recommendation

That the Commission APPROVE the recosted 2019 capital budget of $10,868,500 as summarized below noting the recosted budget reflects the previously approved 2019 capital budget program (Staff Report #2, August 29, 2018), updated pricing for 2019 bus replacement/expansion programs (Staff Report #2, November 28, 2018), and carry forward amounts relating to deferred or active 2018 capital projects.

2019 Recosted Capital Budget

Description  Source of Investment  Total
 Capital Program Reserve  City of London  Federal Gas Tax  Provincial Gas Tax
Stop Upgrades $ 37,000 $ –  $ – $ – $ 37,000
Service Fleet 40,000 40,000
Shop Equipment 200,000 200,000
Software and Hardware 390,000 210,000 600,000
Facility Upgrades 500,000 500,000
Bus Replacements (8) 2,224,800 1,500,000 1,023,200 4,748,000
Bus Expansion (1) 300,100 323,400 623,500
Fleet Radio Replacement 312,500 312,500 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 747,500 747,500 1,495,000
Smart Card Program 500,000 500,000
$ 667,000 $ 4,084,900 $ 1,500,000 $ 4,616,600 $ 10,868,500

Background

At the August 29, 2018 Commission meeting, the 2019 Operating and Capital budget programs were approved (Staff Reports #1 & #2, August 29, 2018). Consistent with established practices, the 2019 budget is subject to a recosting exercise for both capital and operating budgets. The exercise takes into consideration significant trends and/or emergent issues that have developed since the budget was first prepared, including 2018 results, price changes, revenue/ridership trends and program updates. The City of London requested and approved investment is not subject to recosting consideration unless an amendment business case for material items is submitted and approved by Municipal Council.

Capital

At the August 29, 2018 Commission meeting, the 2019 capital budget program of $6,137,900 was approved. A recosting exercise for both capital and operating budgets occurs at the beginning of the year after all City of London funding is confirmed and takes into consideration pricing updates as well as any prior year projects that have not been completed or deferred to the future. The following table provides a summary by project of the proposed updated capital budget highlighting the original approved budget, pricing updates and 2018 carry forwards together with identified funding sources.

Summary of 2019 Recosted Capital Budget

Description Original Approved Budget Adjustments 2018 Carry Forward Total
Program:
Stop Upgrades  $ 37,000  $ –  $ –  $ 37,000
Service Fleet 40,000 40,000
Shop Equipment 200,000 200,000
Software and Hardware 200,000 400,000 600,000
Facility Upgrades 500,000 500,000
Bus Replacements (8) 4,560,800 187,200 4,748,000
Bus Expansion (1) 600,100 23,400 623,500
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 1,495,000 1,495,000
Smart Card Program 500,000 500,000
Total  $ 6,137,900  $ 210,600  $ 4,520,000  $10,868,500
Funding:
Provincial Gas Tax  $ 1,136,100  $ 210,600  $ 3,269,900  $ 4,616,600
Capital Program Reserve 477,000 190,000 667,000
City of London 3,024,800 1,060,100 4,084,900
Federal Gas Tax 1,500,000 1,500,000
Total  $ 6,137,900 $ 210,600  $ 4,520,000  $10,868,500

The capital budget for the 2019 expansion and replacement buses required a recosting increase of $210,600. Pricing updates from New Flyer reflect a 4.2% increase over 2018 prices for 40’ buses and was arrived at by applying the price escalation formula included in the contract. Note, the 2018 price was the value included in the 2019 original budget. Updates to this price were approved by the Commission at its November 28, 2018 meeting (Staff Report #2, Contract Award – 2019 Replacement & Expansion Buses). The following table summarizes the unit price comparison and resulting increases.

Unit Price Comparison

Bus

Size

Buses Budgeted

Price

2018

Price

2019

Price

Price

Increase

40′ 9  $ 545,800  $ 545,800  $ 568,800 $ 23,000

Set out in Enclosure I is the Capital Program Summary for the twelve months ending December 31, 2018. As indicated in the Enclosure, a number of the projects planned for and included in the 2018 capital budget program were not completed in 2018 or have been deferred to future years. Given funds have been approved the outstanding amounts are carried forward to 2019 where necessary. The following table summarizes the 2018 capital expenditures for outstanding projects and the corresponding carry forward amounts, including funding source, for inclusion in the 2019 Capital Program.

Summary of 2018 Carry Forward Capital Projects

Description 2018

Actual

2018

Budget

Variance 2018

Carry

Forward

Program:
Software and hardware  $ 192,843  $ 600,000  $ 407,157  $ 400,000
Fleet radio replacement 625,000 625,000 625,000
TMP 2030 – BRT strategy 1,500,000 1,500,000 1,500,000
Smart card program 97,963 605,000 507,037 500,000
Fare processing equipment 1,495,000 1,495,000 1,495,000
 $ 290,806  $ 4,825,000  $ 4,534,194  $ 4,520,000
Funding:
Provincial Gas Tax  $ 165,866  $ 3,415,000  $ 3,249,134  $ 3,269,900
Capital Program Reserve 124,940 350,000 225,060 190,000
City of London 1,060,000 1,060,000 1,060,100
Total  $ 290,806  $ 4,825,000  $ 4,534,194  $ 4,520,000

The current recommendation has the recosted increases funded by the Provincial Gas Tax Reserve and the carry forwards funded by the original funding sources identified in 2018.

 

Operating

The Commission confirmed the 2019 Operating Budget Submission, as previously approved on August 26, 2015 as part of the multi-year budget submission at the August 29, 2018 Commission meeting, noting the 2019 Operating Budget consists of the following:

Conventional Specialized Total
Total Operating Expenditure  $ 74,688,400  $ 9,281,800  $ 83,970,200
Total Operating Revenue 47,332,600 3,763,400 51,096,000
Total City of London Investment  $ 27,355,800  $ 5,518,400  $ 32,874,200

The process to recost the operating budget for 2019 was undertaken similar to that of prior years. 2018 final year end results were compared to the 2018 projected actual used in the creation of the 2019 budget, with particular attention paid to trends relating to ridership and revenue, fuel pricing and volume fluctuations, as well as labour and benefit trends and service update impacts. The review did not result in the identification of any known factors or trends that would lead to the need to recost the operating budget.

The Commission will be provided with regular updates on the status of the programs included in the 2019

Operating and Capital budgets through the regular monthly reporting process.

Enclosure

I – 2018 Capital Program Summary (below)

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager

2018 Capital Program Summary – Twelve Months Ending December 31, 2018

Description  Total Note
 Capital

 Program

 Reserve

 City of

 London

 Prov Ont

 Gas

 Tax Prog

Stop Upgrades
Actual to-date $ 210,301 $ – $ – $ 210,301
Budget 37,000 73,000  110,000
Variance (137,301) 73,000 (100,301) 1
Service Fleet
Actual to-date 33,971 33,971
Budget 40,000 40,000
Variance 6,029 6,029 2
Shop Equipment
Actual to-date 131,916 131,916
Budget 200,000 200,000
Variance 68,084 68,084 2
Software and Hardware
Actual to-date 124,940 67,903 192,843
Budget 350,000 250,000 600,000
Variance 225,060 182,097 407,157 3
Facility Upgrades
Actual to-date 244,502 244,502
Budget 300,000 300,000
Variance 55,498 55,498 2
Bus Replacements (8)
Actual to-date 3,724,800 823,224 4,548,024
Budget 3,724,800 836,000 4,560,800
Variance  – 12,776 12,776 2
Bus Expansion (4)
Actual to-date 1,200,200 1,143,238 2,343,438
Budget 1,200,200 1,178,200 2,378,400
Variance 34,962 34,962 2
Fleet Radio Replacement
Actual to-date
Budget 312,500 312,500 625,000
Variance 312,500 312,500 625,000 4
TMP 2030 – BRT Strategy
Actual to-date
Budget 1,500,000 1,500,000
Variance 1,500,000 1,500,000 4
Fare Processing Equipment
Actual to-date
Budget 747,500 747,500 1,495,000
Variance 747,500 747,500 1,495,000 4
Smart Card Program
Actual to-date 97,963 97,963
Budget 605,000 605,000
Variance 507,037 507,037 3
Total program
Actual to-date 501,129 5,169,502 2,132,328 7,802,959
Budget 627,000 6,285,000 5,502,200 12,414,200
Variance $ 125,871 $ 1,115,498 $ 3,369,872 $ 4,611,241

Notes:

  1. Program completed, over budget, due to additional stops/cement pads required for significant service changes in 2018
  2. Programs completed, slightly under budget with no carry forward to 2019
  3. Programs not completed. Amount to be carried forward to 2019
  4. Programs deferred, amount to be carry forward to 2019