Staff Report #6 – Financial Update – Capital Budget Programs – August 31, 2026

Staff Report #6

October 19, 2026

To All Commissioners

Re: Financial Update – Capital Budget Programs – August 31, 2026

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2026 Capital Program Summary for the eight-month period ending August 31, 2026.

Summary of 2026 Capital Budget Program Activity Eight Months Ending August 31, 2026

Description  Actual  Budget Amount Under Budget (Over Budget) Project Status
Program
Bus replacement (2026)  $ 18,511,266  $ 17,774,000 $ (737,266) Completed
Bus expansion (ICIP) 11,572,670 11,033,000 (539,670) Completed
Bus expansion 1,052,061 1,003,000 (49,061) Completed
Facility upgrades 383,918 500,000 116,082 In progress
Fare processing equipment 1,582,606 1,936,800 354,194 In progress
Information systems 544,472 1,000,000 455,528 In progress
Shop & garage equipment 145,336 240,000 94,664 In progress
Service fleet replacement 52,085 155,000 102,915 In progress
Stop upgrades 30,935 63,500 32,565 In progress
Bus stop amenities – 167,500 167,500 Pending ICIP approval
Fleet radio replacement – 625,000 625,000 Project deferred
Highbury facility rebuild – 11,670,000 11,670,000 In progress (multi-year)
Zero emission bus pilot – 25,960,000 25,960,000 In progress (multi-year)
Total $ 33,875,349  $ 72,127,800  $ 38,252,451
Funding
Provincial Gas Tax $ 1,114,206 $ 3,571,600 $ 2,457,394
Capital Program Reserve 772,828 1,458,500 685,672
City of London 19,572,954 38,758,000 19,177,506
CPTF 4,126,000 – (4,126,000)
ICIP – Provincial 3,767,895 6,984,900 3,217,005
ICIP – Federal 4,521,926 8,382,800 3,860,874
Senior Government – 12,980,000 12,980,000
Total $ 33,875,349 $ 72,127,800  $ 38,252,451

The following programs are underway or completed through the first eight months of the year, with narrative focusing on the year-to-date progress.

Bus replacement and expansion (29 buses) – All 29 buses have been fully outfitted and placed into service. It should be noted that all three projects have exceeded their approved budgets due solely to additional US tariffs passed on by the manufacturer. With the recently approved allocation of the Canada Public Transit Fund by Council, funding for the above projects has been updated to reflect this modification and all expenditures will be fully funded.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to office renovations, rotary lift installation, a generator and rear hoist refurbishments at Highbury.

Fare processing equipment – The project to replace the OBV’s (on board validators) on the conventional fleet is near completion, with all buses currently on the road having been upgraded. Outstanding payments pertain to the final holdbacks pending clearance of remaining punch list items for both the validator and back-office software upgrades.

Information systems & hardware – Expenditures incurred to date include additions to networking equipment and other hardware purchases.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date are for the purchase of a new Inspector van which has since been outfitted for service.

Administration will continue to monitor actual to budget performance and report to the Commission monthly.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager