Rapid Transit Construction – East London Link

Overview:

East London Link Phase 3C (EL3C) extends from Dundas to Oxford on Highbury. East London Link Phase 4 (EL4) extends from Highbury to Third on Oxford. 

EL3C started in Spring 2024 and has since progressed to near completion. As of September 22, 2025, lane channeling has been reduced, enabling several stops to be reopened. 

EL4 started in Spring 2025. Since then the Fanshawe College Terminal was reconstructed and is now located in front of D building. Please see below for impacts relating to the construction on EL3C and EL4. 

Impacts:

Route 10

Closed Stops 953 Highbury – #923
Highbury south of Oxford NB – #922
Reopened Stops Highbury at Corrine NB – #919
Alternate Stops Oxbury Centre SB – #925
John Paul Secondary School NB – #924

Route 95

Route 95 is currently suspended. Please check back when regular service continues.

Routes 4, 17, 20 & 104

Closed Stops

John Paul Secondary School WB – #1310
Oxbury Centre EB – #1307
Oxford at Highbury EB – #1309
Oxford at Second WB – #1344
Oxford at Second EB – #1343
Reopened Stops Oxford at Mornington EB – #1322
Oxford at Wistow WB – #1362
Oxford at Highbury WB – #1308
Alternate Stops Oxford at Third EB – #1352
Oxford at Third – #1344

Route 36

Closed Stops Oxford at Second EB – #1343
Oxford at Second WB – #1344
Alternate Stops Oxford at Third EB – #1352
Oxford at Third WB – #1353

Route 91

Closed Stops Oxford at Highbury EB – #1309
Reopened Stops Oxford at Highbury WB – #1308
Alternate Stops Oxford at Mornington EB – #1322

Stay up to date on all construction impacts by visiting realtime.londontransit.ca. Updates to anticipated construction timelines and impacts to stops will also be updated here as details are known.