Staff Report #10 – Financial Update – Capital Budget Programs – September 30, 2023

Staff Report #10

October 25, 2023

To All Commissioners

Re: Financial Update – Capital Budget Programs – September 30, 2023

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2023 Capital Program Summary for the nine-month period ending September 30, 2023.

Summary of 2023 Capital Budget Program Activity Nine Months Ending September 30, 2023

Description  Actual  Budget Amount
Under Budget
(Over Budget)
Program
Bus replacement $ 381,230  $ 12,848,300  $ 12,467,070
Facility upgrades 340,519 751,600 411,082
Fare processing equipment – 2,495,000 2,495,000
Information systems & hardware 192,985 1,054,000 861,815
Shop & garage equipment 101,296 200,000 98,704
Service fleet replacement – 130,000 130,000
Stop upgrades 37,651 941,100 903,449
Bus stop amenities 354,125 578,700 224,575
Fleet radio replacement – 625,000 625,000
Smart card program – 450,000 450,000
Highbury facility rebuild – 2,500,000 2,500,000
Total $ 1,407,805  $ 22,574,500  $ 21,166,695
Funding
Provincial Gas Tax $ – $ 7,773,300  $ 7,773,300
Capital Program Reserve 331,932 2,325,900 1,993,968
City of London 816,300 2,815,400 1,999,100
City – Federal Gas Tax – 7,403,000 7,403,000
ICIP – Provincial 117,924 1,025,400 907,476
ICIP – Federal 141,650 1,231,500 1,089,850
Total $ 1,407,805  $ 22,574,500  $ 21,166,695

The following programs are underway through the first nine months of the year, with narrative focusing on the year-to-date progress.

Bus replacement – Some of the peripheral equipment (cameras, AVL) has started to arrive in anticipation of the receipt of replacement buses beginning in December.

Facility upgrades – Expenditures incurred to date for hoist repairs, lighting, security cameras, painting, interior renovations, and drainage work.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

For further details on the above projects whose responsibility fall within Fleet & Facilities, please refer to Staff Report #4, dated October 25, 2023.

Information systems & hardware – Expenditures incurred to date for the purchase of workstations and networking equipment.

Stop upgrades – Expenditures incurred to date relate to pouring of bus stop pads.

Bus stop amenities – Expenditures incurred to date relate to the purchase of bus stop lighting.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager