Staff Report #12 – Financial Update – Capital Budget Programs – March 31, 2020

Staff Report #12

April 29, 2020

To All Commissioners

Re: Financial Update – Capital Budget Programs – March 31, 2020

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2020 Capital Program Summary for the three-month period ending March 31, 2020, noting the budget reflects the Recosted 2020 Capital Budget Program (Staff Report #7, April 29, 2020).

Summary of 2020 Capital Budget Program Activity

Three Months Ending March 31, 2020

Description  Actual  Budget  Amount

Under Budget

(Over Budget)

Program
Stop Upgrades $ –  $ 240,700  $ 240,700
Service Fleet 33,635 130,000 96,365
Shop Equipment 93,973 236,200 142,227
Software and Hardware 26,074 700,000 673,926
Facility Upgrades 27,652 560,600 532,948
Bus Replacement (16) 68,421 9,488,000 9,419,579
Bus Expansion (1)
Bus Stop Amenities 550,000 550,000
Operator Barriers 1,468,900 1,468,900
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 1,862,100 1,862,100
Smart Card Program 325,000 325,000
Total $ 249,755  $ 17,686,500  $ 17,436,745
Funding
Provincial Gas Tax $ – $ 7,351,300  $ 7,351,300
Capital Program Reserve 153,682 1,296,900 1,143,218
City of London 96,073 7,135,000 7,038,927
Federal – ICIP 220,000 220,000
Provincial – ICIP 183,300 183,300
Federal Gas Tax 1,500,000 1,500,000
Total $ 249,755  $ 17,686,500  $ 17,436,745

The following programs are underway through the first three months of the year, with narrative focusing on the year-to-date progress.

Service Fleet – The replacement vehicle for the Inspector fleet was purchased and has been fully outfitted and placed into service. The remaining budget is for a second vehicle and has yet to be sourced.

Shop Equipment – Expenditures incurred to-date relate to the ongoing monthly purchase of shop tools and equipment as well as a scrubber. This budget is utilized throughout the year as equipment and tools are required.

Software and Hardware – Expenditures incurred to-date for the purchasing of workstations and networking equipment.

Facility Upgrades – Expenditures incurred to-date have been for generator upgrades (both facilities), boiler replacement (Wonderland), and an updated sewer connection (Wonderland). A few other projects are underway with the remainder expected to be completed by year end.

Bus Replacements (16) – Expenditures incurred to-date are for a portion of the ancillary equipment. The buses are scheduled for line entry in mid-May providing there are no additional delays. The New Flyer facility was closed for the first two weeks of April.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager