Staff Report #4 – Financial Update – Capital Budget Programs – May 31, 2025

Staff Report #4

July 21, 2025

To All Commissioners

Re: Financial Update – Capital Budget Programs – May 31, 2025

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2025 Capital Program Summary for the five-month period ending May 31, 2025.

Summary of 2025 Capital Budget Program Activity Five Months Ending May 31, 2025

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Bus replacement (2025)  $ 1,834,804  $ 16,399,700  $ 14,564,896
Bus replacement (2024) 3,116,928 15,393,200 12,276,272
Facility upgrades 124,529 500,000 375,471
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 140,348 800,000 659,652
Shop & garage equipment 45,719 235,000 189,281
Service fleet replacement 53,732 65,000 11,268
Stop upgrades 11,958 96,000 84,042
Fleet radio replacement 625,000 625,000
Highbury facility rebuild 5,000,000 5,000,000
Zero emission bus pilot 25,960,000 25,960,000
Total $ 5,328,018  $ 67,568,900  $ 62,240,882
Funding
Provincial Gas Tax $ – $ 4,497,600 4,497,600
Capital Program Reserve 251,756 1,198,000 944,244
City of London 5,076,262 38,230,300 33,154,028
City – Federal Gas Tax 7,000,000 7,000,000
ICIP – Provincial 1,665,000 1,665,000
ICIP – Federal 2,000,000 2,000,000
Senior Government 12,980,000 12,980,000
Total $ 5,328,018 $ 67,568,900  $ 62,240,882

The following programs are underway through the first five months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2024 & 2025) – Nearly $1 million of ancillary equipment for both programs was received in 2024 and has since been allocated to the appropriate projects. At the time of writing, 20 buses have been received and seven have been outfitted for service. The remaining 14 buses are expected to continue to arrive on a weekly basis, with the final delivery expected by mid-fall.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to additional work on the bus fueling and wash lane at the Wonderland facility, along with other minor repairs and maintenance projects.

Fare processing equipment – At the May 9, 2025 Commission meeting, the project to replace the conventional bus fleet’s OBV’s (on board validators) was approved. At the time of writing, a kick-off meeting with the assigned project management team has been scheduled. At this time, it is expected a timeline for the project will be discussed. Ongoing updates regarding the project will be included in this report on a monthly basis.

Information systems & hardware – Expenditures incurred to date include the networking equipment, Transit Master system upgrades as well as payments for the Specialized scheduling system’s passenger portal module.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van which has been outfitted for service.

Stop upgrades – Expenditures incurred to date pertain to the purchase of replacement glass for shelters.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager