Staff Report #7 – Financial Update – Capital Budget Programs – May 31, 2021

Staff Report #7

June 30, 2021

To All Commissioners

Re: Financial Update – Capital Budget Programs – May 31, 2021

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2021 Capital Program Summary for the five-month period ending May 31, 2021.

Summary of 2021 Capital Budget Program Activity Five Months Ending May 31, 2021

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Stop Upgrades $ –  $ 743,700  $ 743,700
Service Fleet 36,198 50,000 13,802
Shop Equipment 38,556 200,000 161,444
Software and Hardware 91,886 680,000 588,114
Facility Upgrades 129,256 500,000 370,744
Bus Replacements 121,514 10,619,900 10,498,386
Bus Expansion 29,736 1,300,400 1,270,664
Bus Stop Amenities 1,100,000 1,100,000
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 2,495,000 2,495,000
Smart Card Program 295,000 295,000
Total $ 447,146  $ 20,109,000  $ 19,661,854
Funding
Provincial Gas Tax $ 29,736 $ 6,615,700  $ 6,585,964
Capital Program Reserve 166,640 1,463,700 1,297,060
City of London 250,770 7,403,400 7,152,630
Federal – ICIP 960,200 960,200
Provincial – ICIP 800,000 800,000
Federal Gas Tax 2,866,000 2,866,000
Total $ 447,146  $ 20,109,000  $ 19,661,854

The following programs are underway through the first five months of the year, with narrative focusing on the year-to-date progress.

Service Fleet – The replacement vehicle for the Inspector fleet was purchased and has been fully outfitted and placed into service.

Shop Equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and equipment.

Software and Hardware – Expenditures incurred to date for the purchasing of workstations and networking equipment as well as upgrades to the Kronos timekeeping system in Fleet and Facilities.

Facility Upgrades – Expenditures incurred to date for the replacement of doors in C-Barn, upgrades to the lighting at Wonderland as well as upgrades to the fueling system.

Bus Replacement & Expansion – Expenditures incurred to date for ancillary equipment pertaining to both the replacement and expansion bus projects. As a result of the third wave of the pandemic, factory shutdowns by the manufacturer and its suppliers have further impacted the delivery schedule of the new buses. At the time of writing five buses have arrived with one more expected during the week ending June 26, 2021. Further updates will follow as delivery timelines are confirmed beyond these initial six deliveries.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.