Staff Report #14 April 25, 2018

 

To All Commissioners

Re: Financial Update – Capital Budget Programs – March 31, 2018

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2018 Capital Program Summary for the three month period ending March 31, 2018.

 

Summary of 2018 Capital Budget Program Activity

Three Months Ending March 31, 2018

 Amount
 Over Budget
Description  Actual  Budget  (Under Budget)
Program
Stop Upgrades $ 21,278  $ 37,000  $ 15,722
Service Fleet 33,971 40,000 6,029
Shop Equipment 15,568 200,000 184,432
Software and Hardware 96,897 600,000 503,103
Facility Upgrades 300,000 300,000
Bus Replacement (8) 4,560,800 4,560,800
Bus Expansion (4) 20,080 2,378,400 2,358,320
Fleet Radio Replacement 625,000 625,000
TMP 2030 – BRT Strategy 1,500,000 1,500,000
Fare Processing Equipment 1,495,000 1,495,000
Smart Card Program 605,000 605,000
Total $ 187,796  $ 12,341,200  $ 12,153,404
Funding
Provincial Gas Tax $ 40,907 $ 5,429,200  $ 5,388,293
Capital Program Reserve 126,808 627,000 500,192
City of London 20,080 4,785,000 4,764,920
Federal Gas Tax 1,500,000 1,500,000
Total $ 187,796  $ 12,341,200  $ 12,153,404

 

The following programs are underway through the first three months of the year.

Stop Upgrades

The costs incurred to date are attributable to the remaining expenditures from the 2017 shelter installs. As outlined in Staff Report #2, dated April 25, 2018, an additional $73,000 is requested to carry out the planned 2018 shelter program. This addition along with the remaining $15,700 will enable the purchase and installation of 10 shelters.

Service Fleet

The costs incurred to date are attributable to the purchase of a new service van. Outstanding expenditures are related to the lighting kits and ancillary equipment required for the van. See Staff Report #8, dated April 25, 2018.

Shop Equipment

Expenditures incurred to date relate to the ongoing monthly purchase of shop tools. The items indicated in Staff Report #8, dated April 25, 2018 as completed all currently have invoices outstanding.

Software and Hardware

The costs incurred to date are attributable to the replacement of the Specialized scheduling system and other workstation and networking equipment replacements. Work on these projects is scheduled to continue for the remainder of the year.

Bus Purchases

The costs incurred to date are attributable to the early purchase of ancillary equipment required for the 2018 bus expansion and replacement projects. Staff Report #8, dated April 25, 2018 discusses the timing and issues related to these programs.

The remaining programs are scheduled to commence in the remainder of 2018. Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor – Director of Finance

Concurred in by:

Kelly S. Paleczny –  General Manager