Staff Report #14 – Financial Update – Capital Budget Programs – March 31, 2026

Staff Report #14

April 27, 2026

To All Commissioners

Re: Financial Update – Capital Budget Programs – March 31, 2026

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2025 Capital Program Summary for the nine-month period ending March 31, 2026.

Summary of 2025 Capital Budget Program Activity Three Months Ending March 31, 2026

Description  Actual  Budget Amount Under Budget (Over Budget) Project Status
Program
Bus replacement (2026)  $ –  $ 17,774,000 $ 17,774,000 In progress
Bus expansion (ICIP) 11,033,000 11,033,000 In progress
Bus expansion 1,003,000 1,003,000 In progress
Facility upgrades 121,231 500,000 378,769 In progress
Fare processing equipment 104,277 1,936,800 1,823,523 In progress
Information systems 148,183 1,000,000 851,817 In progress
Shop & garage equipment 32,875 240,000 207,125 In progress
Service fleet replacement 52,085 155,000 102,915 In progress
Stop upgrades 63,500 63,500 In progress
Bus stop amenities 167,500 167,500 Pending ICIP approval
Fleet radio replacement 625,000 625,000 Project deferred
Highbury facility rebuild 11,670,000 11,670,000 In progress (multi-year)
Zero emission bus pilot 25,960,000 25,960,000 In progress (multi-year)
Total $ 458,651  $ 72,127,800  $ 71,669,149
Funding
Provincial Gas Tax $ 52,139 $ 3,571,600 $ 3,519,461
Capital Program Reserve 233,143 1,458,500 1225,357
City of London 173,369 38,758,000 38,576,631
ICIP – Provincial 6,984,900 6,984,900
ICIP – Federal 8,382,800 8,382,800
Senior Government 12,980,000 12,980,000
Total $ 458,651 $ 72,127,800  $ 71,669,149

The following programs are underway through the first three months of the year, with narrative focusing on the year-to-date progress.

Bus replacement and expansion (29 buses) – The first bus has recently arrived with delivery of the remaining 28 units expected to begin in May through July. The Fleet & Facilities department have begun preparing the bus for service and will become busy when two to three buses begin arriving on a weekly basis.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to office renovations, rotary lift installation, and a generator. See Staff Report #5, dated April 27, 2026, for further details and plans for the remainder of the year.

Fare processing equipment – The project to replace the OBV’s (on board validators) on the conventional fleet is underway with the costs included above pertaining to software design and development milestones. See Staff Report #7, dated April 27, 2026, for further details.

Information systems & hardware – Expenditures incurred to date include additions to networking equipment and other hardware purchases.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date are for the purchase of a new Inspector van which has since been outfitted for service.

Administration will continue to monitor actual to budget performance and report to the Commission monthly.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager