Staff Report #5 – Financial Update – Capital Budget Programs – July 31, 2026

Staff Report #5

August 31, 2026

To All Commissioners

Re: Financial Update – Capital Budget Programs – July 31, 2026

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2026 Capital Program Summary for the seven-month period ending July 31, 2026.

Summary of 2026 Capital Budget Program Activity Seven Months Ending July 31, 2026

Description  Actual  Budget Amount Under Budget (Over Budget) Project Status
Program
Bus replacement (2026)  $ 18,511,266  $ 17,774,000 $ (737,266) In progress
Bus expansion (ICIP) 11,572,670 11,033,000 (539,670) In progress
Bus expansion 1,052,061 1,003,000 (49,061) In progress
Facility upgrades 339,378 500,000 160,622 In progress
Fare processing equipment 923,137 1,936,800 1,013,663 In progress
Information systems 544,472 1,000,000 455,528 In progress
Shop & garage equipment 58,968 240,000 181,032 In progress
Service fleet replacement 52,085 155,000 102,915 In progress
Stop upgrades 3,969 63,500 59,531 In progress
Bus stop amenities 167,500 167,500 Pending ICIP approval
Fleet radio replacement 625,000 625,000 Project deferred
Highbury facility rebuild 11,670,000 11,670,000 In progress (multi-year)
Zero emission bus pilot 25,960,000 25,960,000 In progress (multi-year)
Total $ 33,058,006  $ 72,127,800  $ 39,069,794
Funding
Provincial Gas Tax $ 454,737 $ 3,571,600 $ 3,118,863
Capital Program Reserve 659,494 1,458,500 799,006
City of London 19,527,954 38,758,000 19,922,046
CPTF 4,126,000 (4,126,000)
ICIP – Provincial 3,767,895 6,984,900 3,217,005
ICIP – Federal 4,521,926 8,382,800 3,860,874
Senior Government 12,980,000 12,980,000
Total $ 33,058,006 $ 72,127,800  $ 39,069,794

The following programs are underway through the first seven months of the year, with narrative focusing on the year-to-date progress.

Bus replacement and expansion (29 buses) – At the time of writing, all buses are on property with 15 outfitted for service and currently on the road. The remaining buses will be placed into service when available. It should be noted that all projects will exceed the approved budgeted amounts solely a result of the additional US tariffs passed on by the manufacturer. With the recently approved allocation of the Canada Permanent Transit Fund by Council, funding for the above projects has been updated to reflect this modification and all expenditures are fully funded.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to office renovations, rotary lift installation, a generator and rear hoist refurbishments at Highbury.

Fare processing equipment – The project to replace the OBV’s (on board validators) on the conventional fleet is near completion, with all buses currently on the road having been upgraded. Outstanding payments pertain to a portion of the billing for the installation as well as the final holdbacks pending project acceptance for both the validator and back office software upgrades.

Information systems & hardware – Expenditures incurred to date include additions to networking equipment and other hardware purchases.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date are for the purchase of a new Inspector van which has since been outfitted for service.

Administration will continue to monitor actual to budget performance and report to the Commission monthly.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager