Staff Report #3 – Financial Update – Capital Budget Programs – April 30, 2025

Staff Report #3

June 23, 2025

To All Commissioners

Re: Financial Update – Capital Budget Programs – April 30, 2025

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2025 Capital Program Summary for the four-month period ending April 30, 2025.

Summary of 2025 Capital Budget Program Activity Four Months Ending April 30, 2025

Description  Actual  Budget Amount Under Budget (Over Budget)
Program
Bus replacement (2025)  $ 502,418  $ 16,399,700  $ 15,897,282
Bus replacement (2024) 423,005 15,393,200 14,970,195
Facility upgrades 119,350 500,000 380,650
Fare processing equipment 2,495,000 2,495,000
Information systems & hardware 100,419 800,000 699,581
Shop & garage equipment 37,530 235,000 197,470
Service fleet replacement 53,732 65,000 11,268
Stop upgrades 11,958 96,000 84,042
Fleet radio replacement 625,000 625,000
Highbury facility rebuild 5,000,000 5,000,000
Zero emission bus pilot 25,960,000 25,960,000
Total $ 1,248,411  $ 67,568,900  $ 66,320,489
Funding
Provincial Gas Tax $ – $ 4,497,600 4,497,600
Capital Program Reserve 203,638 1,198,000 992,362
City of London 1,044,773 38,230,300 37,185,527
City – Federal Gas Tax 7,000,000 7,000,000
ICIP – Provincial 1,665,000 1,665,000
ICIP – Federal 2,000,000 2,000,000
Senior Government 12,980,000 12,980,000
Total $ 1,248,411 $ 67,568,900  $ 66,320,489

The following programs are underway through the first four months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2024 & 2025) – Nearly $1 million of ancillary equipment for both programs was received in 2024 and has since been allocated to the appropriate projects. At the time of writing, 11 buses have been received and three have been outfitted for service. The remaining 23 buses are expected to continue to arrive on a weekly basis, with the final delivery expected by mid-fall.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to additional work on the bus fueling and wash lane at the Wonderland facility, along with other minor repairs and maintenance projects.

Fare processing equipment – At the May 9, 2025 Commission meeting, the project to replace the conventional bus fleet’s OBV’s (on board validators) was approved. The vendor, Scheidt & Bachmann has indicated that a project schedule will be provided to LTC approximately 60 days after project approval. Ongoing updates regarding the project will be included in this report on a monthly basis.

Information systems & hardware – Expenditures incurred to date include the networking equipment, Transit Master system upgrades as well as payments for the Specialized scheduling system’s passenger portal module.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van which has been outfitted for service.

Stop upgrades – Expenditures incurred to date pertain to the purchase of replacement glass for shelters.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager