Staff Report #8 – Financial Update – Capital Budget Programs – May 31, 2026

Staff Report #8

June 29, 2026

To All Commissioners

Re: Financial Update – Capital Budget Programs – May 31, 2026

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2026 Capital Program Summary for the five-month period ending May 31, 2026.

Summary of 2026 Capital Budget Program Activity Five Months Ending May 31, 2026

Description  Actual  Budget Amount

Under Budget (Over Budget)

Project Status
Program
Bus replacement (2026)  $ 3,773,631  $ 17,774,000 $ 14,000,369 In progress
Bus expansion (ICIP) 10,377,486 11,033,000 655,514 In progress
Bus expansion 943,408 1,003,000 59,592 In progress
Facility upgrades 185,755 500,000 314,245 In progress
Fare processing equipment 559,325 1,936,800 1,377,475 In progress
Information systems 198,338 1,000,000 801,662 In progress
Shop & garage equipment 47,692 240,000 192,308 In progress
Service fleet replacement 52,085 155,000 102,915 In progress
Stop upgrades 63,500 63,500 In progress
Bus stop amenities 167,500 167,500 Pending ICIP approval
Fleet radio replacement 625,000 625,000 Project deferred
Highbury facility rebuild 11,670,000 11,670,000 In progress (multi-year)
Zero emission bus pilot 25,960,000 25,960,000 In progress (multi-year)
Total $ 16,137,720  $ 72,127,800  $ 55,990,080
Funding
Provincial Gas Tax $ 279,663 $ 3,571,600 $ 3,291,937
Capital Program Reserve 298,115 1,458,500 1,160,385
City of London 7,950,131 38,758,000 30,799,869
ICIP – Provincial 3,458,817 6,984,900 3,526,083
ICIP – Federal 4,150,994 8,382,800 4,231,806
Senior Government 12,980,000 12,980,000
Total $ 16,137,720 $ 72,127,800  $ 55,990,080

The following programs are underway through the first five months of the year, with narrative focusing on the year-to-date progress.

Bus replacement and expansion (29 buses) – At the time of writing, all but two buses are on property with six outfitted for service and currently on the road. The remaining buses are expected to be in service prior to the September service change implementation.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to office renovations, rotary lift installation, and a generator.

Fare processing equipment – The project to replace the OBV’s (on board validators) on the conventional fleet is underway and on schedule, with the costs included above pertaining to software design and development milestones.

Information systems & hardware – Expenditures incurred to date include additions to networking equipment and other hardware purchases.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date are for the purchase of a new Inspector van which has since been outfitted for service.

Administration will continue to monitor actual to budget performance and report to the Commission monthly.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager