Staff Report #9 – Financial Update – Capital Budget Programs – September 30, 2025

Staff Report #9

October 27, 2025

To All Commissioners

Re: Financial Update – Capital Budget Programs – September 30, 2025

Recommendation

That the report be RECEIVED for information.

Background

Summarized in the table below is the 2025 Capital Program Summary for the nine-month period ending September 30, 2025. Consistent with the changes made for the August report, additional detail has been provided with respect to capital projects and the status of each.

Summary of 2025 Capital Budget Program Activity Nine Months Ending September 30, 2025

Description  Actual  Budget Amount Under Budget (Over Budget) Project Status
Program
Bus replacement (2025)  $ 16,502.068  $ 16,399,700 $ (102,368) In progress
Bus replacement (2024) 15,495,532 15,393,200 (102,332) In progress
Facility upgrades 239,106 500,000 260,894 In progress
Fare processing equipment 558,200 2,495,000 1,936,800 In progress (multi-year)
Information systems 249,349 800,000 550,651 In progress
Shop & garage equipment 87,215 235,000 147,785 In progress
Service fleet replacement 53,732 65,000 11,268 Project complete
Stop upgrades 61,159 96,000 34,841 In progress
Fleet radio replacement 625,000 625,000 Project deferred
Highbury facility rebuild 5,000,000 5,000,000 In progress (multi-year)
Zero emission bus pilot 25,960,000 25,960,000 In progress (multi-year)
Total $ 33,246,361  $ 67,568,900  $ 34,322,539
Funding
Provincial Gas Tax $ 2,642,301 $ 4,497,600 $ 1,855,299
Capital Program Reserve 451,454 1,198,000 744,546
City of London 23,152,606 38,230,300 15,077,694
City – Federal Gas Tax 7,000,000 7,000,000
ICIP – Provincial 1,665,000 1,665,000
ICIP – Federal 2,000,000 2,000,000
Senior Government 12,980,000 12,980,000
Total $ 33,246,361 $ 67,568,900  $ 34,322,539

The following programs are underway through the first eight months of the year, with narrative focusing on the year-to-date progress.

Bus replacement (2024 & 2025) – All 34 buses have arrived with only a few remaining invoices outstanding. At the time of writing, 28 buses have been outfitted for service and are currently on the road. Both projects have come in slightly over budget due mainly to additional tariffs charged on the bus build, noting the Provincial Gas Tax reserve fund will be utilized to fund this shortfall.

Facility upgrades – The facility upgrade program is underway with costs incurred to date pertaining to additional work on the bus fueling and wash lane at the Wonderland facility, along with many other minor repairs and maintenance projects. Asphalt repairs at the Wonderland facility are currently in progress. See Staff Report #4, dated October 27, 2025, for further details.

Fare processing equipment – The project to replace the OBV’s (on board validators) on the conventional fleet is underway with the costs included above pertaining to the first and second payment milestones (completed design documentation). The next milestone, expected to occur in May 2026, coincides with the shipment of the devices.

Information systems & hardware – Expenditures incurred to date include the networking equipment, Transit Master system upgrades as well as payments for the Specialized scheduling system’s passenger portal module.

Shop and garage equipment – Expenditures incurred to date relate to the ongoing monthly purchase of shop tools and miscellaneous equipment within Fleet & Facilities.

Service fleet replacement – Expenditures incurred to date relate to the purchase of a new Inspector van which has been outfitted for service. This program is entirely funded by the Commission’s Capital Program Reserve and as such, an excess budget remains in the reserve for future years’ programs.

Stop upgrades – Expenditures incurred to date pertain to concrete pads, the purchase of replacement glass for shelters as well as additional sign installations. The 2025 program is expected to be completed by year end.

Administration will continue to monitor actual to budget performance and report to the Commission monthly.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager