Staff Report #8 – Financial Update – Capital Budget Programs – June 30, 2020

Staff Report #8

July 29, 2020

To All Commissioners

Re: Financial Update – Capital Budget Programs – June 30, 2020

Recommendation

That the report be NOTED and FILED.

Background

Summarized in the table below is the 2020 Capital Program Summary for the six-month period ending June 30, 2020.

Summary of 2020 Capital Budget Program Activity

Six Months Ending June 30, 2020

Description Actual  Budget Amount Under Budget (Over Budget)
Program
Stop Upgrades$ – $ 240,700 $ 240,700
Service Fleet73,839130,00056,161
Shop Equipment109,434236,200126,766
Software and Hardware26,074700,000673,926
Facility Upgrades57,182560,600503,418
Bus Replacement (16)92,4489,488,0009,395,552
Bus Expansion (1)
Bus Stop Amenities550,000550,000
Operator Barriers1,468,9001,468,900
Fleet Radio Replacement625,000625,000
TMP 2030 – BRT Strategy1,500,0001,500,000
Fare Processing Equipment1,862,1001,862,100
Smart Card Program29,330325,000295,670
Total$ 388,307 $ 17,686,500 $ 17,298,193
Funding
Provincial Gas Tax$ 29,330$ 7,351,300 $ 7,321,970
Capital Program Reserve209,3481,296,9001,087,552
City of London149,6297,135,0006,985,371
Federal – ICIP220,000220,000
Provincial – ICIP183,300183,300
Federal Gas Tax1,500,0001,500,000
Total$ 388,307 $ 17,686,500 $ 17,298,193

The following programs are underway through the first six months of the year, with narrative focusing on the year-to-date progress.

Service Fleet – The replacement vehicle for the Inspector fleet was purchased and has been fully outfitted and placed into service. A van was purchased for the mobile mechanic function and is currently being outfitted with racking, lighting, etc.

Shop Equipment – Expenditures incurred to-date relate to the ongoing monthly purchase of shop tools and equipment as well as a scrubber. This budget is utilized throughout the year as equipment and tools are required.

Software and Hardware – Expenditures incurred to-date for the purchasing of workstations and networking equipment.

Facility Upgrades – Expenditures incurred to-date have been for generator upgrades (both facilities), boiler replacement (Wonderland), an updated sewer connection (Wonderland), repairs to damaged columns (Highbury), and HVAC upgrades in the server room. A few other projects are underway with the remainder expected to be completed by year-end.

Bus Replacements (16) – Expenditures incurred to-date are for a portion of the ancillary equipment. The buses are scheduled for line entry in mid-July. Providing there are no additional delays at the New Flyer facility, delivery is set to commence in late September.

Smart Card Program – additional replacement routers purchased.

Administration will continue to monitor actual to budget performance and report to the Commission on a monthly basis.

Recommended by:

Mike Gregor, Director of Finance

Concurred in by:

Kelly S. Paleczny, General Manager