Construction season is starting with work taking place at several locations across the city, which will impact bus stops and transit routes. Work includes major infrastructure renewal and road reconstruction projects which may require temporary detours and stop relocations. Riders may experience changes while this work is underway. Please see the project details and impacts below for more information on affected areas and timelines.
York St Infrastructure Renewal Project
The York St Infrastructure Renewal Project will focus on reconstructing York St from Wellington to Colborne, including intersection improvements. Construction will be completed in two stages:
- Stage 1: York St between Wellington and Colborne
- Stage 2: York St and Colborne St intersection
Anticipated to start the week of March 16 – find detour details.
- Location: York between Wellington and Colborne
- Impacts: Route 7
- Closed Stops: All Stops on York between Wellington and Colborne
The East London Link is a multi-year infrastructure project that will rebuild roads between downtown and Fanshawe College while adding dedicated transit lanes and improving transportation.
East London Link Phase 5 includes work along Dundas Street from McCormick Boulevard to just east of Highbury Avenue.
Anticipated to start the week of March 16 – find detour details.
- Location: Dundas between Highbury and Egerton
- Impacts: Routes 2 & 94
- Closed Stops: All Stops on Dundas between Egerton and Highbury
The closure of Hubrey includes utility work to replace leaking valves. Enbridge will be on-site completing repair work and excavation.
Anticipated to start the week of March 16 – find detour details.
- Location: Hubrey between Enterprise and Wilton Grove
- Impacts: Route 30
- Closed Stops: All Stops on Hubrey between Enterprise and Wilton Grove
Make sure to check the Detours & Stop Closures page and as always, before heading out check realtime.londontransit.ca.